CJ Jimmy Leow observed the progress of the once abandoned highway located at Balik Pulau, Penang. The highway which connects the little town of Balik Pulau to Teluk Kumbar has resumed construction recently by Sarahon Construction which will cost the government an additional 42 million ringgit.
Previously, the original cost of the highway was 56 million ringgit but abandoned by Bulkers Corporation due to financial problem in the early months of 2008. At this point of time, 40 million ringgit has been spent.
Instead of paying the original cost of 56 million ringgit, the government now had to pay 82 million ringgit for the same project, which is a 46% increase. Instead of completing the project in Sept 2008, it is now scheduled to be completed at the end of 2010.